BHP’s first-quarter copper output falls 19% as iron ore production rises
BHP said copper production fell 19% year on year to 400,700 tonnes in July–September, while iron ore rose 4% to 66.5 million tonnes. The miner left its FY2027 production guidance unchanged.
In its 20 October operational review for the quarter ended 30 September, BHP reported first-quarter FY2027 copper production of 400,700 tonnes, down 19% from a year earlier. The company attributed the decline to planned lower feed grades, maintenance, severe weather in Chile, safety stoppages and a conveyor failure at Carrapateena. Iron ore output rose 4% to 66.5 million tonnes, steelmaking coal increased 1% to 4.9 million tonnes and energy coal rose 26% to 4.4 million tonnes.
BHP left production guidance unchanged across its main commodities. WAIO reported records at both its mine and port, while Stage 1 of the Jansen potash project was 87% complete and remained on track for first production in mid-2027. The company also reported the deaths of two colleagues at Escondida and Peak Downs, with investigations underway. The figures are BHP’s own operational reporting; one quarter’s volumes alone do not establish a future production or price trend.
HABER PAPER / DATA
Behind the numbers
Inspect the source, read the data, make your own analysis.
Data table
BHP production, Q1 FY27
BHP-reported production and year-on-year changes for the quarter ended 30 September 2026.
BHP production, Q1 FY27
Indicator
Value
Unit
Period start
Period end
Comparison basis
Copper production — Q1 FY27 production
400.7
kt
2026-07
2026-09
observed
Copper production — year-on-year change
-19
% year over year
2026-07
2026-09
observed
Iron ore production — Q1 FY27 production
66.5
million tonnes
2026-07
2026-09
observed
Iron ore production — year-on-year change
4
% year over year
2026-07
2026-09
observed
Steelmaking coal — Q1 FY27 production
4.9
million tonnes
2026-07
2026-09
observed
Steelmaking coal — year-on-year change
1
% year over year
2026-07
2026-09
observed
Energy coal — Q1 FY27 production
4.4
million tonnes
2026-07
2026-09
observed
Energy coal — year-on-year change
26
% year over year
2026-07
2026-09
observed
Source and methodology
Haber Paper source-linked editorial data compilation; underlying sources retain their separate reuse terms.
Three holes were drilled at its Patterson Lake North project in Saskatchewan; the company cautions that the readings are not uranium grades and assays remain pending.
Natural Resources Minister Tim Hodgson met U.K. officials and companies during London Metal Exchange Week to discuss energy, investment and mineral supply chains.
Google Analytics can measure visits and site activity using cookies if you allow it. You can change your choice later.
Measurement and privacy details
Google Analytics measurement starts only if you allow it. After consent, automatic measurement may cover scrolls, outbound link clicks, downloads, video engagement, site searches and basic form interactions; search terms may be detected from URL parameters. This site’s own code does not send form field values; email redaction in automatic measurement is best-effort, not guaranteed. Our manual page-view event uses a cleaned URL. You can change your choice later. Visits that begin with consent may also send numeric LCP, INP and CLS performance measurements after Analytics loads. A first or later grant starts this on the next page load; withdrawing consent stops these performance reports for this page. The preference cookie lasts six months; advertising measurement and personalization stay off.
Your browser is sending a Global Privacy Control signal. Analytics is off by default; you may explicitly change this choice here.