{"version":"1","article":{"id":"statnett-kvandal-kilbotn-420kv-planning-october-2026","slug":"statnett-kvandal-kilbotn-420kv-planning-october-2026","language":"ar","url":"https://haberpaper.com/ar/news/statnett-kvandal-kilbotn-420kv-planning-october-2026","api_url":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=ar","title":"ستاتنت تبدأ تخطيط خط 420 كيلوفولت لتعزيز إمدادات شمال النرويج","summary":"بدأت ستاتنت التخطيط لخط 420 كيلوفولت بين كفاندال وكيلبوتن لتعزيز الإمداد في لوفوتن وفيستيرولن وهارستاد، مع استهداف إخطار NVE في 2027.","category":"energy","region":"world","topics":[],"published_at":"2026-10-10T15:42:15+03:00","modified_at":"2026-10-10T15:42:15+03:00","publication_basis":"publication-record","event_period":"2026-10-06","event_period_basis":"event-or-reference-period","sources":[{"name":"Statnett — Planning starts for new Kvandal–Kilbotn line","url":"https://www.statnett.no/vare-prosjekter/region-nord/kvandal--kilbotn/nyhetsarkiv/starter-planleggingen-av-ny-kraftledning-for-a-oppgradere-stromnettet-i-lofoten-vesteralen-og-harstadomradet/","publishedAt":"2026-10-06","checkedAt":"2026-10-10"},{"name":"Statnett — Planning starts for new Kvandal–Kilbotn line","url":"https://www.statnett.no/vare-prosjekter/region-nord/kvandal--kilbotn/","publishedAt":"2026-10-06","checkedAt":"2026-10-10"}],"translations":[{"language":"tr","url":"https://haberpaper.com/tr/news/statnett-kvandal-kilbotn-420kv-planning-october-2026","api_url":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=tr"},{"language":"en","url":"https://haberpaper.com/en/news/statnett-kvandal-kilbotn-420kv-planning-october-2026","api_url":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=en"},{"language":"ar","url":"https://haberpaper.com/ar/news/statnett-kvandal-kilbotn-420kv-planning-october-2026","api_url":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=ar"},{"language":"fr","url":"https://haberpaper.com/fr/news/statnett-kvandal-kilbotn-420kv-planning-october-2026","api_url":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=fr"},{"language":"es","url":"https://haberpaper.com/es/news/statnett-kvandal-kilbotn-420kv-planning-october-2026","api_url":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=es"}],"data_types":["metrics"],"data":{"version":1,"blocks":[{"id":"statnett-kvandal-kilbotn-420kv-planning-october-2026","type":"metrics","title":{"tr":"Kvandal–Kilbotn 420 kV hattı için planlama başladı","en":"Statnett begins planning 420 kV Kvandal–Kilbotn line","ar":"ستاتنت تبدأ تخطيط خط 420 كيلوفولت لتعزيز إمدادات شمال النرويج","fr":"Statnett lance la planification d’une ligne de 420 kV Kvandal–Kilbotn","es":"Statnett inicia la planificación de la línea de 420 kV Kvandal–Kilbotn"},"description":{"tr":"Statnett, Lofoten, Vesterålen ve Harstad bölgesinin elektrik şebekesini güçlendirmek için yeni hattı planlıyor; henüz yatırım veya inşaat kararı yok.","en":"Statnett started planning a 420 kV Kvandal–Kilbotn line to strengthen supply in Lofoten, Vesterålen and Harstad, with notification to NVE planned for 2027.","ar":"بدأت ستاتنت التخطيط لخط 420 كيلوفولت بين كفاندال وكيلبوتن لتعزيز الإمداد في لوفوتن وفيستيرولن وهارستاد، مع استهداف إخطار NVE في 2027.","fr":"Statnett a lancé la planification d’une ligne de 420 kV entre Kvandal et Kilbotn pour renforcer l’approvisionnement de Lofoten, Vesterålen et Harstad ; l’avis à NVE est prévu en 2027.","es":"Statnett inició la planificación de una línea de 420 kV entre Kvandal y Kilbotn para reforzar el suministro de Lofoten, Vesterålen y Harstad; prevé notificar a NVE en 2027."},"methodology":{"tr":"Kapasite artışı, tüketim ve bağlantı rezervasyonları Statnett’in proje planlamasındaki tahmin ve hedefleridir; hat için izin ve nihai güzergâh belirlenmemiştir.","en":"Regional demand estimates and the recommended capacity package from Statnett’s project page; final line capacity and investment decision have not yet been set.","ar":"تقديرات الطلب الإقليمي وحزمة السعة الموصى بها في صفحة المشروع؛ ولم تُحدد بعد السعة النهائية للخط أو قرار الاستثمار.","fr":"Estimations de demande régionale et paquet de capacité recommandé par Statnett ; la capacité définitive de la ligne et l’investissement ne sont pas encore arrêtés.","es":"Estimaciones de demanda regional y paquete recomendado por Statnett; la capacidad definitiva y la inversión aún no se han decidido."},"sourceUrls":["https://www.statnett.no/vare-prosjekter/region-nord/kvandal--kilbotn/nyhetsarkiv/starter-planleggingen-av-ny-kraftledning-for-a-oppgradere-stromnettet-i-lofoten-vesteralen-og-harstadomradet/","https://www.statnett.no/vare-prosjekter/region-nord/kvandal--kilbotn/"],"updatedAt":"2026-10-10T12:25:07Z","items":[{"label":{"tr":"Tavsiye edilen paket için kapasite artışı tahmini","en":"Estimated capacity increase for recommended package","ar":"الزيادة المقدرة في سعة الحزمة الموصى بها","fr":"Hausse de capacité estimée pour le paquet recommandé","es":"Aumento de capacidad estimado del paquete recomendado"},"value":50,"unit":"percent","period":"2026-10-06","basis":"estimate","measure":{"id":"statnett-kvandal-capacity-increase","unitCode":"percent","geography":"norway","frequency":"irregular","aggregation":"rate","periodRole":"announcement-date"}},{"label":{"tr":"Bölge için kapasitesi ayrılmış proje sayısı","en":"Projects with capacity reserved in the region","ar":"المشروعات ذات السعة المحجوزة في المنطقة","fr":"Projets disposant d’une capacité réservée dans la région","es":"Proyectos con capacidad reservada en la región"},"value":20,"unit":"count","period":"2026-10-06","basis":"estimate","measure":{"id":"statnett-kvandal-capacity-reservations","unitCode":"count","geography":"norway","frequency":"irregular","aggregation":"stock","periodRole":"announcement-date"}}]}]},"data_compilations":[{"id":"statnett-kvandal-kilbotn-420kv-planning-october-2026","creator":{"@type":"Organization","@id":"https://haberpaper.com/#organization","name":"Haber Paper","url":"https://haberpaper.com/"},"license":{"@type":"CreativeWork","@id":"https://haberpaper.com/en/data-terms/v1#license","name":"Haber Paper Original Data Compilation License 1.0","url":"https://haberpaper.com/en/data-terms/v1"},"rights_scope":"Haber Paper original data arrangement, labels and methodology notes only; underlying source rights and permissions remain separate.","source_license_url":null}],"data_downloads":[{"id":"statnett-kvandal-kilbotn-420kv-planning-october-2026","formats":{"json":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026/data/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=ar&format=json","csv":"https://haberpaper.com/api/v1/articles/statnett-kvandal-kilbotn-420kv-planning-october-2026/data/statnett-kvandal-kilbotn-420kv-planning-october-2026?lang=ar&format=csv"}}],"content":{"paragraphs":["أعلنت ستاتنت في 6 أكتوبر بدء التخطيط لخط كهرباء جديد بجهد 420 كيلوفولت بين كفاندال وكيلبوتن في شمال النرويج. ويهدف المشروع إلى تعزيز الشبكة التي تغذي هارستاد وجزر لوفوتن وفيستيرولن، حيث تقول ستاتنت إن طلبات الأنشطة الاقتصادية الجديدة تتجاوز قدرة الشبكة الحالية. كما تخطط الشركة لتجديد محطة كيلبوتن. ويبدأ الإعلان مرحلة التخطيط، ولا يمثل تصريحاً أو قراراً بالإنشاء.","جاء اختيار 420 كيلوفولت بعد دراسة بدائل بالتعاون مع شركات الشبكات الإقليمية. وتوصي ستاتنت بالتنفيذ على مراحل، مع اعتبار خط كفاندال–كيلبوتن الخطوة الأولى. وتوضح صفحة المشروع أن الخط سيُصمم لمستوى 420 كيلوفولت، لكنه سيُشغّل عند 132 كيلوفولت في البداية. فجهد التصميم وجهد التشغيل أمران مختلفان، ولا تعني الخطة تشغيل الخط فوراً عند 420 كيلوفولت.","تقول ستاتنت إن حزمة الإجراءات الموصى بها في الدراسة يمكن أن ترفع سعة المنطقة 50%. وتشير الشركة إلى أن عدة تعزيزات إقليمية قيد الإنشاء أو التخطيط وأن تطوير الشبكة ينبغي أن يواكب الاحتياجات. ونسبة 50% تقدير لحزمة الإجراءات، وليست سعة متاحة بالفعل أو نتيجة لهذا الخط وحده. كما يلزم معالجة اختناقات أخرى بين هيلغلاند وسالتن لنقل الكهرباء الإضافية إلى أقصى الشمال.","ووفق صفحة المشروع، ارتفع استهلاك المنطقة بنحو 20% خلال بضع سنوات. وتقول ستاتنت إن السعة حُجزت لنحو 20 مشروعاً صناعياً وتجارياً يتوقع ربطها خلال السنوات المقبلة، كما تشير إلى احتياجات الدفاع. وتفسر الأرقام سبب التخطيط لكنها لا تضمن تنفيذ كل مشروع. وتهدف الشركة إلى إخطار هيئة NVE في منتصف 2027 تقريباً؛ وهذه محطة تخطيط وتقييم وليست موعد تشغيل.","وبعد الإخطار، يتعين على NVE إجراء مشاورات ووضع برنامج لتقييم الأثر البيئي قبل النظر في طلب الترخيص الكامل. ويمكن للبلديات والجهات العامة والمجتمعات المتأثرة المشاركة. وتقول ستاتنت إن التخطيط سيستمر بالتعاون مع مشغل الشبكة الإقليمي نورانيت. ولم يُعلن عند نشر الخبر عن مسار تفصيلي نهائي أو تكلفة استثمار أو جدول بناء أو تاريخ تشغيل. ولم يحدد البيان مصادر التمويل أو الجهة التي ستدفع التكاليف النهائية، كما لم يضع تقديراً منشوراً لمقدار الاستثمار. وستتطلب أي توسعة تقييم الآثار البيئية ومراجعة خيارات المسار قبل الترخيص. لذلك تظل أرقام السعة والطلب معلومات تخطيطية."],"key_points":[],"sections":[]},"text":"بدأت ستاتنت التخطيط لخط 420 كيلوفولت بين كفاندال وكيلبوتن لتعزيز الإمداد في لوفوتن وفيستيرولن وهارستاد، مع استهداف إخطار NVE في 2027.\n\nأعلنت ستاتنت في 6 أكتوبر بدء التخطيط لخط كهرباء جديد بجهد 420 كيلوفولت بين كفاندال وكيلبوتن في شمال النرويج. ويهدف المشروع إلى تعزيز الشبكة التي تغذي هارستاد وجزر لوفوتن وفيستيرولن، حيث تقول ستاتنت إن طلبات الأنشطة الاقتصادية الجديدة تتجاوز قدرة الشبكة الحالية. كما تخطط الشركة لتجديد محطة كيلبوتن. ويبدأ الإعلان مرحلة التخطيط، ولا يمثل تصريحاً أو قراراً بالإنشاء.\n\nجاء اختيار 420 كيلوفولت بعد دراسة بدائل بالتعاون مع شركات الشبكات الإقليمية. وتوصي ستاتنت بالتنفيذ على مراحل، مع اعتبار خط كفاندال–كيلبوتن الخطوة الأولى. وتوضح صفحة المشروع أن الخط سيُصمم لمستوى 420 كيلوفولت، لكنه سيُشغّل عند 132 كيلوفولت في البداية. فجهد التصميم وجهد التشغيل أمران مختلفان، ولا تعني الخطة تشغيل الخط فوراً عند 420 كيلوفولت.\n\nتقول ستاتنت إن حزمة الإجراءات الموصى بها في الدراسة يمكن أن ترفع سعة المنطقة 50%. وتشير الشركة إلى أن عدة تعزيزات إقليمية قيد الإنشاء أو التخطيط وأن تطوير الشبكة ينبغي أن يواكب الاحتياجات. ونسبة 50% تقدير لحزمة الإجراءات، وليست سعة متاحة بالفعل أو نتيجة لهذا الخط وحده. كما يلزم معالجة اختناقات أخرى بين هيلغلاند وسالتن لنقل الكهرباء الإضافية إلى أقصى الشمال.\n\nووفق صفحة المشروع، ارتفع استهلاك المنطقة بنحو 20% خلال بضع سنوات. وتقول ستاتنت إن السعة حُجزت لنحو 20 مشروعاً صناعياً وتجارياً يتوقع ربطها خلال السنوات المقبلة، كما تشير إلى احتياجات الدفاع. وتفسر الأرقام سبب التخطيط لكنها لا تضمن تنفيذ كل مشروع. وتهدف الشركة إلى إخطار هيئة NVE في منتصف 2027 تقريباً؛ وهذه محطة تخطيط وتقييم وليست موعد تشغيل.\n\nوبعد الإخطار، يتعين على NVE إجراء مشاورات ووضع برنامج لتقييم الأثر البيئي قبل النظر في طلب الترخيص الكامل. ويمكن للبلديات والجهات العامة والمجتمعات المتأثرة المشاركة. وتقول ستاتنت إن التخطيط سيستمر بالتعاون مع مشغل الشبكة الإقليمي نورانيت. ولم يُعلن عند نشر الخبر عن مسار تفصيلي نهائي أو تكلفة استثمار أو جدول بناء أو تاريخ تشغيل. ولم يحدد البيان مصادر التمويل أو الجهة التي ستدفع التكاليف النهائية، كما لم يضع تقديراً منشوراً لمقدار الاستثمار. وستتطلب أي توسعة تقييم الآثار البيئية ومراجعة خيارات المسار قبل الترخيص. لذلك تظل أرقام السعة والطلب معلومات تخطيطية.","corrections":[],"editorial_illustration":{"kind":"symbolic-editorial-illustration","documentary":false,"scope":"section","asset_id":"energy","url":"https://haberpaper.com/assets/illustrations/energy-1536.webp","width":1536,"height":1024,"alt":"مشهد رمزي للطاقة يجمع الألواح الشمسية وتوربينات الرياح وخطوط النقل.","language":"ar"},"section_illustration":{"kind":"symbolic-editorial-illustration","documentary":false,"scope":"section","asset_id":"energy","url":"https://haberpaper.com/assets/illustrations/energy-1536.webp","width":1536,"height":1024,"alt":"مشهد رمزي للطاقة يجمع الألواح الشمسية وتوربينات الرياح وخطوط النقل.","language":"ar"}}}